Leisure Centre progress update
If you have passed our site recently you will see that the precast cladding panels and new window installation has progress in the last few weeks, the building façade is really taking shape and will shortly be watertight. At roof level we have started installing the mesh panels around the new roof level sports pitches. Elsewhere on the Leisure Centre the new swimming pool area concrete shells are nearing completion ready for water testing, the drylining works have started to the new indoor six-court sports hall and as you can see from the photos below this will be a great space once its complete. The squash court and new start of the art gym areas are being prepared for the fit out works to commence in the next few months.