Site cabins delivery
In the coming three weeks we will be installing our main site office cabins.
On the first day of each phase, we’ll have a mobile crane arrive on site at 7am under a plant movement order. This is due to the size of the machinery being used, which requires a plant movement order from the Metropolitan Police. As the plant is an abnormal large load, it requires a police escort and therefore must travel outside peak times.
The mobile crane will drive onto the site and park up until 8am when it will commence works. It will then remain on site overnight then leave the following night at 7pm, again this will be under a plant movement order.
All vehicles involved in these works will follow the route marked in red on the map below.
The first phase of works will start on Tuesday 16 July and be completed by the end of the day on Wednesday 17 July.
The second phase starts on Tuesday 23 July and will be complete by Wednesday 24 July.
Finally, the third phase starts on Tuesday 30 July, completing by Wednesday 31 July.
On each day the cabins are being delivered, the parking bays on Northport Street will be suspended – this is to give the lorry delivering the cabins sufficient space to manoeuvre. The disabled bays on Gopsall Street will remain in use throughout these works.
You can view the full text regarding this work in our letter to residents.